With only one week to go now until Easter, the superstructure of the house is nearing completion. The brickies should complete the block work in the w/c 30/3 and the roof trusses are due on site on 2/4.
Most of the window openings are now fully framed and the full size and shape of the house is now there to be seen. JS Geddes, our kitchen supplier have also just sent us a pack with full details of the kitchen specification and layout.
Sunday, 29 March 2015
Friday, 20 March 2015
Week 18: Final steelwork now in situ
![]() |
| Steels form the lounge window opening |
![]() | |||
| Joe surveys the build from the scaffold platform |
We're probably running a few weeks behind schedule now, mainly due to bad weather. Next week sees Bernhard & the brickie back on site to finish the block work and then the following week should see the beginning of the installation of the roof.
Sunday, 15 March 2015
Week 17: The Joiners have arrived!
They've started laying the first floor platform and strapping the walls.
It's now possible to get sense of the room sizes and overall layout of the building.
![]() |
| Susan checks the hall for size |
![]() |
| One of the joiners laying the engineered floor joists |
![]() |
| The upstairs floor starts to take shape |
All, hopefully, this side of the Easter weekend.
Saturday, 28 February 2015
Week 15: Blockwork nears completion
Friday, 20 February 2015
Week 14: Landscaping the site
Our architect Ewan Cameron has been busy this week producing a few rough ideas for the eventual landscaping 'look & feel' for the site.
As we have a sloping site the use of terracing seems to be most appropriate and will make best use of the garden.
This image gives an impression of how the site & house may look eventually.
As we have a sloping site the use of terracing seems to be most appropriate and will make best use of the garden.
This image gives an impression of how the site & house may look eventually.
Week 14: Ground floor walls built and window openings formed
Sunday, 15 February 2015
Week 13: 'The brickies are back'
The past few weeks have been painfully slow progress on site - mainly down to snow, ice and sub-zero temperatures. Bernhard and the boys had been eager to make a start but there was no way they could mix mortar and expect it to set safely when 'it's Baltic outside'.
With an increase in temperature on Monday this week a team of brickies arrived back on site and got to work like a team 'possessed'. By the end of the week they've pretty much laid out all of the ground floor walls and doorways.
Dougie from PAN builders has also been able to confirm the dimensions for the first floor joists and get them ordered for a few weeks time.
The brickies 'crack on next week' and we should see the walls continue to rise and the window openings formed.
![]() |
| "...just like icing a cake" |
![]() |
| "many hands make light work" |
![]() | |
| Joe breaks the ice on a frozen water bucket |
With an increase in temperature on Monday this week a team of brickies arrived back on site and got to work like a team 'possessed'. By the end of the week they've pretty much laid out all of the ground floor walls and doorways.
![]() |
| It's not a building site without a Lucozade bottle |
![]() |
| The view of the ground floor from high above Joe's bedroom |
The brickies 'crack on next week' and we should see the walls continue to rise and the window openings formed.