With only one week to go now until Easter, the superstructure of the house is nearing completion. The brickies should complete the block work in the w/c 30/3 and the roof trusses are due on site on 2/4.
Most of the window openings are now fully framed and the full size and shape of the house is now there to be seen. JS Geddes, our kitchen supplier have also just sent us a pack with full details of the kitchen specification and layout.
Sunday, 29 March 2015
Friday, 20 March 2015
Week 18: Final steelwork now in situ
![]() |
Steels form the lounge window opening |
![]() | |||
Joe surveys the build from the scaffold platform |
We're probably running a few weeks behind schedule now, mainly due to bad weather. Next week sees Bernhard & the brickie back on site to finish the block work and then the following week should see the beginning of the installation of the roof.
Sunday, 15 March 2015
Week 17: The Joiners have arrived!
They've started laying the first floor platform and strapping the walls.
It's now possible to get sense of the room sizes and overall layout of the building.
![]() |
Susan checks the hall for size |
![]() |
One of the joiners laying the engineered floor joists |
![]() |
The upstairs floor starts to take shape |
All, hopefully, this side of the Easter weekend.